How long does exterior painting take in South Florida?

What decides the calendar on an exterior repaint here: crew size, the coating's recoat window, stucco cure times, rain and dew — with the figures.

Published Updated 6-minute read

Three to four working days for a one- or two-story house with a crew of two or three; five to six for a large three-story [1]. Two things stretch that here: the recoat window — 4 hours for acrylic, 24 hours for elastomeric [2][3] — and stucco repair, which cures one to six weeks before paint [7].

Key numbers

  • Typical house, crew of two or three: 3–4 days; large three-story home: 5–6 days [1]
  • Recoat windows: Duration Exterior 4 hours, Loxon XP 24 hours, Aura Exterior 4 hours, Perma-Crete 1–2 hours [2][3][4][5]
  • Rain: do not apply if rain is expected within 2–3 hours; keep conditions in range and above the dew point for 48 hours after application [2][6]
  • After heavy rain: wait a minimum of one day, and the surface must be dry [6]
  • Stucco repairs: 1–6 weeks to cure before painting [7]; new stucco 30 days, or 7 days over a masonry primer [2][7]
  • South Florida rainy season: May 15 – October 15 [8]
  • Fort Lauderdale rainfall normals: 9.92 in in June against 2.36 in in February [9]

Where the days actually go

On a house, painting is the short part. The order of work is cleaning, repair, masking, priming where the substrate needs it, then coats — and the first two days go to the first two of those [1]. A crew that arrives and starts spraying on the morning of day one is not fast; it is skipping the part that decides whether the film is still attached in five years.

That is also why "how long does it take?" and "what does it cost?" have the same answer underneath: the condition of the wall. A sound, clean, recently maintained exterior is a short job. One with chalking, open cracks and failed sealant is a long one, and no extra crew wins those days back.

The shape of a typical week

On a two-story house with sound walls and a crew of two or three, the sequence usually falls out like this [1]:

DayWork
1Wash the building; protect landscaping, fixtures and paving
2Repairs, caulking and sealant; let patches begin curing
3Mask, prime where the substrate needs it, start the first coat
4Finish the first coat; second coat where the recoat window allows
5Trim, doors, detail work, walkthrough and punch list

Anything that lengthens that is one of four things: repairs that have to cure, a coating with a long recoat window, weather, or a wall that turns out to be worse than it looked from the ground. The first three are predictable and belong in the schedule. The fourth is why a good estimate says what happens if the quantities change.

The coating decides the calendar

CoatingDry to touchRecoatSource
SW Duration Exterior1 hour4 hours[2]
SW Loxon XP (elastomeric-type)4 hours24 hours[3]
BM Aura Exterior1 hour4 hours[4]
PPG Perma-Crete30 minutes1–2 hours[5]

Those are the manufacturers' own figures at moderate temperature and 50% relative humidity [2][3][4][5]. The one that changes a schedule is Loxon XP's 24-hour recoat [3]: a two-coat waterproofing system on a stucco house is two calendar days of coating minimum, before weather, where the same house in a standard acrylic could take both coats in one day.

Every one of those data sheets carries the same warning in different words — high humidity and cool temperatures make dry, recoat and service times longer [4]. In August, in Broward, they are longer.

Rain, dew and the 48-hour rule

Sherwin-Williams's guidance is not to apply if rain is expected within 2–3 hours, and to keep the temperature in range and above the dew point for at least 48 hours after application [2][6]. After heavy rain, its FAQ says to wait a minimum of one day and to confirm the surface is dry before painting [6].

Dew is the part that surprises people who have painted elsewhere. On a clear South Florida night, dew forms on almost everything as soon as the sun sets, and it will seep into a film that has not finished curing [6]. That is why exterior work here stops well before dark rather than at dark, and why afternoon coats in the rainy season are a decision rather than a default.

Repairs cure on their own clock

Angi puts stucco repairs at 1–6 weeks of cure before they can be painted [7]. New stucco is stricter: Sherwin-Williams asks for 30 days, or 7 days if a masonry primer is used first; Benjamin Moore also specifies 30 days for new masonry; PPG asks for 7 days minimum and prefers 30 [2][4][5].

This is the single largest reason a repaint quote and a repaint schedule are different documents. If the walls need work, the paint date is set by the repair, not by the crew's calendar.

The season you pick changes the length

The National Weather Service defines the South Florida rainy season as May 15 to October 15 [8], and the rainfall normals for Fort Lauderdale show what that means for a schedule: about 9.92 inches in June and 8.11 inches in September against 2.36 inches in February [9]. The same house painted in March and in August is not the same number of working days, because in August some of them are not working days.

Condos and communities

A multi-building community is normally phased rather than painted at once. Industry descriptions put a full program at 18–36 months building by building, with washing and touch-up cycles every 5–7 years [10]; that is a contractor's account rather than a survey, and we cite it as one.

Where a repaint follows a structural inspection, the statute sets a date that overrides everybody's preference: repairs recommended in a Phase Two milestone report must be commenced within 365 days of the association receiving the report [11]. Painting and waterproofing usually sit at the end of that sequence, after the concrete work, which is why boards that plan the coating last often find they have less calendar than they thought.

What shortens it

Three things, all decided before the crew arrives. Clear access — cars moved, gates unlocked, furniture and planters away from the walls — removes a surprising amount of standing around. Color decisions made and approved in writing, especially where an association palette is involved, keep the job from pausing between the first coat and the second. And repairs surveyed and started early cure while other work carries on, instead of holding up the coating at the end.

How Smart Coat handles this

Our schedules name the constraint. If the wall needs repair, the estimate says how long the repair has to cure before it can be coated, and the paint dates follow it rather than the other way around. If the specification is an elastomeric system, the recoat window is in the schedule as a day, not as an inconvenience.

We also write weather into the plan rather than around it — mornings in the rainy season, no coats going on that cannot cure before dew, and named catch-up days rather than a promise nobody can keep in July.

More on exterior painting, stucco repair and HOA and community painting, or read how a project runs. When you are ready, ask us to look at the job.

Sources

Every figure above is numbered to one of these. Each carries the date the source itself published or last updated it.

  1. PPG — Perma-Crete Technical Data Bulletin 4-503

    buyat.ppg.com

  2. Sherwin-Williams — Exterior Product Application FAQs

    sherwin-williams.com

About the author

Florida Certified General Contractor #CGC1534419 · Florida DBPR

Written and maintained by Smart Coat Painting & Construction, a licensed Florida general contractor working from Miami to West Palm Beach. We publish under the company name rather than a byline, because the company is answerable for what is on the page.

More about Smart Coat

FAQ

Common questions

Short answers first. If yours is not here, ask us — we would rather answer it than guess at it.

How long does it take to paint a 2,000 sq ft house exterior?

Three to four working days for a one- or two-story home with a crew of two or three, and five to six days for a larger three-story house, is the industry's working figure [1]. In South Florida, add time for anything the walls need before coating and for weather: an elastomeric system on stucco needs 24 hours between coats [3] where a standard exterior acrylic needs 4 [2], which by itself adds days to the same house.

How long should exterior paint dry between coats?

It depends on the product and it is published on every data sheet. Sherwin-Williams Duration recoats at 4 hours; Loxon XP, the waterproofing masonry coating, at 24 hours; Benjamin Moore Aura Exterior at 4 hours at 77°F and 50% relative humidity; PPG Perma-Crete at 1–2 hours [2][3][4][5]. All of those assume moderate humidity — every one of the sheets says high humidity and cool temperatures make the numbers longer.

What happens if it rains after painting?

Sherwin-Williams advises against applying if rain is expected within 2–3 hours, and asks that conditions stay in range and above the dew point for at least 48 hours after application [2][6]. After heavy rain the company's own FAQ says to wait a minimum of one day, and that the surface must be dry before painting regardless [6]. Fresh film caught by rain inside that window can blister, streak or wash.

Can you paint a house exterior in one day?

Not properly, on a whole house. The first day or two of a competent exterior is cleaning, repair and masking, and coats only start after that [1]. Even where the coating recoats in 4 hours [2], a house has more wall than a crew can prepare, cut and coat between sunrise and dew.

Why does stucco repair add weeks to the schedule?

Because cement cures on its own clock. Angi puts stucco repairs at 1–6 weeks to cure before they can be painted [7]. New stucco is worse: Sherwin-Williams asks for 30 days of cure before painting, or 7 days if a masonry primer is used; Benjamin Moore also asks 30 days; PPG asks 7 days minimum and prefers 30 [2][4][5]. A schedule that paints a fresh patch the next day is buying a blister.

How long does it take to repaint a condo or HOA community?

Multi-building communities are normally phased building by building rather than done at once, over a period reported at 18–36 months, with washing and touch-up cycles every 5–7 years [10] — an industry description rather than a survey, so treat it as shape and not schedule. Where the work follows a milestone inspection, statute sets its own clock: repairs recommended by a Phase Two report must commence within 365 days of the report [11].